Decatur St. Sidewalk Update: July 7, 2017

The City of New Orleans’ construction contractor, Hard Rock Construction, continues installing sidewalks along Decatur St. The overall project is approximately 45% completed and is anticipated to be completed by mid-August 2017, weather permitting.

The scope of work includes:

  • Removing and replacing sidewalks along the 800 – 1300 blocks of Decatur St.
  • Installing Americans with Disabilities Act-compliant curb ramps.
  • Installing access ramps for impacted storefronts / residents during construction.
  • Temporary disruptions to access of storefronts for approximately one hour during concrete pours and brick installation.
  • Temporary lane shift.
  • No street parking during work hours.

 1000 blocks of Decatur St.

(river side)  – Work is scheduled to be completed on Tuesday, July, 11, weather permitting.

1100 blocks of Decatur St.

(lake side) – All work is completed.

(river side) –  Work is scheduled to begin on Wednesday, July 12, weather permitting.

 1300 (river side) blocks of Decatur St.

(lake side) – All work is completed.

(river side)  – All work is scheduled to be completed on Tuesday, July, 11, weather permitting.

For questions or concerns contact RoadworkNOLA at 504.658.ROAD (7623) or roadwork@nola.gov.