The City of New Orleans’ construction contractor, Hard Rock Construction, continues installing sidewalks along Decatur St. The overall project is approximately 45% completed and is anticipated to be completed by mid-August 2017, weather permitting.
The scope of work includes:
1000 blocks of Decatur St.
(river side) – Work is scheduled to be completed on Tuesday, July, 11, weather permitting.
1100 blocks of Decatur St.
(lake side) – All work is completed.
(river side) – Work is scheduled to begin on Wednesday, July 12, weather permitting.
1300 (river side) blocks of Decatur St.
(lake side) – All work is completed.
(river side) – All work is scheduled to be completed on Tuesday, July, 11, weather permitting.
For questions or concerns contact RoadworkNOLA at 504.658.ROAD (7623) or roadwork@nola.gov.